Measurement Analysis of Box Girder Production Cycle Times in Indonesia Infrastructure Projects

Authors
Verly Widiantoro, Mohammad Ichsan, Pungky Dharma Saputra
Corresponding Author
Verly Widiantoro
Available Online 11 August 2021.
DOI
10.2991/aer.k.210810.002How to use a DOI?
Keywords
Box Girder, Cycle Times, Production, Scheduling
Abstract

Infrastructure is one of the important elements in the development of a country. The number of bridge infrastructure projects that can increase the growth of the construction industry in Indonesia must be supported by construction technology as well as the use of precast box girders. Problems arise due to inaccurate planning and production scheduling of box girders which cause the project delay. For this reason, it is necessary to carry out an analysis of the measurement of the box girder production cycle times as soon as possible hence it can provide an overview and reference in planning and scheduling elevated infrastructure projects. The purpose of this research is to measure the box girder production cycle times in Indonesian infrastructure projects. The main variable is the box girder production cycle time. The projects observed were projects in the last 3 years from 2016 to 2020. And the production of the box girder segments chosen were box girder segments with straight alignment. The average analysis is used to know the average of the cycle times. Based on descriptive analysis, the average production cycle time is 38.95 hours with an average delay time of 6.28 hours. The average production cycle time can be used as a reference for planning and developing schedules for elevated infrastructure projects.

Copyright
© 2021, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2nd Borobudur International Symposium on Science and Technology (BIS-STE 2020)
Series
Advances in Engineering Research
Publication Date
11 August 2021
ISBN
10.2991/aer.k.210810.002
ISSN
2352-5401
DOI
10.2991/aer.k.210810.002How to use a DOI?
Copyright
© 2021, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Verly Widiantoro
AU  - Mohammad Ichsan
AU  - Pungky Dharma Saputra
PY  - 2021
DA  - 2021/08/11
TI  - Measurement Analysis of Box Girder Production Cycle Times in Indonesia Infrastructure Projects
BT  - Proceedings of the 2nd Borobudur International Symposium on Science and Technology (BIS-STE 2020)
PB  - Atlantis Press
SP  - 6
EP  - 10
SN  - 2352-5401
UR  - https://doi.org/10.2991/aer.k.210810.002
DO  - 10.2991/aer.k.210810.002
ID  - Widiantoro2021
ER  -