Proceedings of the 2015 International Conference on Intelligent Systems Research and Mechatronics Engineering

The construction methods of Bridge crane rail on Underground powerhouse

Authors
Bo Yang, Yunyun Zhang, Zhaoxia Li
Corresponding Author
Bo Yang
Available Online April 2015.
DOI
10.2991/isrme-15.2015.39How to use a DOI?
Keywords
Underground powerhouse Bridge machine Bridge crane rail Track installation Construction organization Rock anchored crane beam
Abstract

It is difficult to construct the underground powerhouse in technology, and which also faces other aspects such as higher construction requirement and shorter construction period. If the bridge crane rail can be come into service, the bridge machine will become promptly forces to be put into operation, that can help to take a big role in encouraging the transportation speeds of materials and equipment in underground powerhouse.Of course bridge machine, which can speed up the construction progress, occupies an important position in the transport construction of underground powerhouse.Taking the construction of bridge machine as a research object, it describes the construction procedure for bridge crane rail installation in this paper, provides certain reference for the organization of the underground powerhouse concrete construction.

Copyright
© 2015, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2015 International Conference on Intelligent Systems Research and Mechatronics Engineering
Series
Advances in Intelligent Systems Research
Publication Date
April 2015
ISBN
10.2991/isrme-15.2015.39
ISSN
1951-6851
DOI
10.2991/isrme-15.2015.39How to use a DOI?
Copyright
© 2015, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Bo Yang
AU  - Yunyun Zhang
AU  - Zhaoxia Li
PY  - 2015/04
DA  - 2015/04
TI  - The construction methods of Bridge crane rail on Underground powerhouse
BT  - Proceedings of the 2015 International Conference on Intelligent Systems Research and Mechatronics Engineering
PB  - Atlantis Press
SP  - 169
EP  - 173
SN  - 1951-6851
UR  - https://doi.org/10.2991/isrme-15.2015.39
DO  - 10.2991/isrme-15.2015.39
ID  - Yang2015/04
ER  -