Research on the Standard of Site Management Fee Claim for Schedule Delay Based on Engineering Construction Contract (2013)

Authors
Wenxiu Bu, Hong Ke
Corresponding Author
Wenxiu Bu
Available Online April 2016.
DOI
10.2991/icemct-16.2016.149How to use a DOI?
Keywords
delay of construction period; site management fee; claim
Abstract

Currently, the disputes on expense claim problems caused by delay of construction period between the employer and contractor in the project is very common. Such situation can be caused by lacking of clear standards on expense claim problems between the employers and contractors. For the above phenomenon, through literature research and combination with the engineering construction contract (model text)(13 list),this paper divides the factors that influence delay of construction period and analyzes the construction of the site management fee claim for schedule delay, then researches the calculation method of the site management fees, which is beneficial to solve the problems caused by delay of construction period effectively.

Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2016 International Conference on Education, Management and Computing Technology (ICEMCT-16)
Series
Advances in Social Science, Education and Humanities Research
Publication Date
April 2016
ISBN
10.2991/icemct-16.2016.149
ISSN
2352-5398
DOI
10.2991/icemct-16.2016.149How to use a DOI?
Copyright
© 2016, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Wenxiu Bu
AU  - Hong Ke
PY  - 2016/04
DA  - 2016/04
TI  - Research on the Standard of Site Management Fee Claim for Schedule Delay Based on Engineering Construction Contract (2013)
BT  - Proceedings of the 2016 International Conference on Education, Management and Computing Technology (ICEMCT-16)
PB  - Atlantis Press
SP  - 685
EP  - 690
SN  - 2352-5398
UR  - https://doi.org/10.2991/icemct-16.2016.149
DO  - 10.2991/icemct-16.2016.149
ID  - Bu2016/04
ER  -