Proceedings of the International Conference on Maritime and Archipelago (ICoMA 2018)

The Identification of Risk Factors of Delay On The Road Construction Project in Indonesia

Authors
Asri Nurdiana, Mohamad Agung Wibowo, Yulian Fundra Kurnianto
Corresponding Author
Asri Nurdiana
Available Online October 2019.
DOI
10.2991/icoma-18.2019.82How to use a DOI?
Keywords
Risk Management, Road Project, Factors of Delay Project
Abstract

In the construction of road projects, there are risks in, especially related to the time of project. This is a concern because in its construction, road projects are often related to social impact in the society, such as the road closures, the route changes, etc. The delay in road projects will impact not only to the contractor and the project owner, but also to the society. The purpose of this research is to identify the risk factors that cause delay in the road construction project. Meanwhile, the purpose of this study is to identify risk factors that affect the occurrence of delay in road projects from the perspective of contractor. The method used in this research was quantitative descriptive method. The primary data used in this study were obtained through survey method, questionnaire, and interview. While the secondary data obtained through literature studies previous studies and existing project data. Data processing method in this research use Risk Breakdown Structure for risk factor causing delay in road project.

Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the International Conference on Maritime and Archipelago (ICoMA 2018)
Series
Advances in Engineering Research
Publication Date
October 2019
ISBN
10.2991/icoma-18.2019.82
ISSN
2352-5401
DOI
10.2991/icoma-18.2019.82How to use a DOI?
Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Asri Nurdiana
AU  - Mohamad Agung Wibowo
AU  - Yulian Fundra Kurnianto
PY  - 2019/10
DA  - 2019/10
TI  - The Identification of Risk Factors of Delay On The Road Construction Project in Indonesia
BT  - Proceedings of the International Conference on Maritime and Archipelago (ICoMA 2018)
PB  - Atlantis Press
SP  - 384
EP  - 387
SN  - 2352-5401
UR  - https://doi.org/10.2991/icoma-18.2019.82
DO  - 10.2991/icoma-18.2019.82
ID  - Nurdiana2019/10
ER  -