Abstract

The traditional construction method of a nuclear power plant is to build a factory building and a containment, and then put the key structure into the containment. From the AP1000 project, the open-top construction scheme is adopted. The open-top method can quickly hoist key structure, but the construction process, tooling and other equipment need to be changed. It is challenging for units that have no open top construction experience. This paper simulates the overall assembly and hoisting construction of the bottom pool for a nuclear power project. For the overall assembled tooling, the design scheme is verified; for the overall lifting of the pool, the problem of the construction plan is discovered in advance, and the hoisting construction plan is improved.

Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2019 International Conference on Modeling, Simulation, Optimization and Numerical Techniques (SMONT 2019)
Series
Advances in Intelligent Systems Research
Publication Date
April 2019
ISBN
10.2991/smont-19.2019.12
ISSN
1951-6851
DOI
10.2991/smont-19.2019.12How to use a DOI?
Copyright
© 2019, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Jianguang Li
AU  - Yibo Fan
AU  - Xuanyu Sheng
AU  - Lanwen Wang
PY  - 2019/04
DA  - 2019/04
TI  - Simulation of Hoisting Bottom Pool of Nuclear Power Plant by Open-Top Construction Method
BT  - Proceedings of the 2019 International Conference on Modeling, Simulation, Optimization and Numerical Techniques (SMONT 2019)
PB  - Atlantis Press
SP  - 46
EP  - 50
SN  - 1951-6851
UR  - https://doi.org/10.2991/smont-19.2019.12
DO  - 10.2991/smont-19.2019.12
ID  - Li2019/04
ER  -