Abstract

The aim of this preliminary research is to study the precision of pile foundation position compared to its original designed location. Before the installation of steel pipe piles for this project, the subcontractor found that the present vessel and equipment could not fully satisfy the plan twist angle and inclination requirements as shown on the detailed design drawings. Adjustment to the twist angle was needed for individual piles in some pier locations. In connection to the pile positions after the adjustment, this research has compared the pile forced loads with that of the original layout, and found that the structural impact is very insignificant due to the change in twist angle. It is confirmed that the revised pile group layout is acceptable. The relevant detail design is still applicable and amendment is unnecessary. The recommendation of this research could be adopted for the similar huge marine structures which installed large diameter steel pipe piles.

Copyright
© 2018, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Download article (PDF)

Volume Title
Proceedings of the 2017 3rd International Forum on Energy, Environment Science and Materials (IFEESM 2017)
Series
Advances in Engineering Research
Publication Date
February 2018
ISBN
10.2991/ifeesm-17.2018.153
ISSN
2352-5401
DOI
10.2991/ifeesm-17.2018.153How to use a DOI?
Copyright
© 2018, the Authors. Published by Atlantis Press.
Open Access
This is an open access article distributed under the CC BY-NC license (http://creativecommons.org/licenses/by-nc/4.0/).

Cite this article

TY  - CONF
AU  - Kang Huang
PY  - 2018/02
DA  - 2018/02
TI  - A Research for special piers' adjustment of steel pipe pile position: A case of Penang second marine bridge
BT  - Proceedings of the 2017 3rd International Forum on Energy, Environment Science and Materials (IFEESM 2017)
PB  - Atlantis Press
SP  - 812
EP  - 817
SN  - 2352-5401
UR  - https://doi.org/10.2991/ifeesm-17.2018.153
DO  - 10.2991/ifeesm-17.2018.153
ID  - Huang2018/02
ER  -